Payment and Draw Schedule Calculator

A deposit, a set of progress draws and a final payment, worked out in dollars and cumulative percentages, then handed to you as a printable schedule you can attach to the contract.

It does not stop at a number.

When the figures look right, the payment schedule downloads as a real PDF with your business details on it, built inside your own browser. Nothing you type is uploaded anywhere.

Contractdraw 1draw 2draw 3draw 4signing to completioncontract, less deposit and final, split evenly across the draws
A draw schedule is cash flow written down before the job starts. Deposit and final come off the top, the rest splits evenly across the milestones, and retainage comes out of each draw rather than the end.

Worked example

These are the figures the calculator opens with and the answer it gives. Change anything above and every number below moves with it.

  • Contract amount180000 $
  • Deposit at signing10 %
  • Number of progress draws after the deposit4
  • Final payment at completion10 %
  • Retainage held from each draw0 %

Each progress draw$36,000.00

Deposit at signing$18,000.0010%
Draw 1$36,000.00cumulative $54,000.00, 30% of contract
Draw 2$36,000.00cumulative $90,000.00, 50% of contract
Draw 3$36,000.00cumulative $126,000.00, 70% of contract
Draw 4$36,000.00cumulative $162,000.00, 90% of contract
Final payment at completion$18,000.0010%

The draw schedule this produces

Deposit at signing1
Progress draw 11
Progress draw 21
Progress draw 31
Progress draw 41
Final payment at completion1

What this calculator assumes

  • Several states cap the deposit a residential contractor may take, some at 10 percent and some at a flat dollar figure. Check your own state before you write a bigger number here.
  • Draws should follow milestones you can point at, not dates. "On completion of rough in inspection" is collectable. "On 15 October" is an argument.
  • A final payment under 10 percent gives the customer no reason to sign off, and one over 20 leaves you funding their job.

Tie draws to milestones, never to dates

On completion of rough in inspection is a draw you can collect. On 15 October is an argument about whose fault the weather was.

Milestones are visible, verifiable and neutral. Both sides can look at the job and agree whether the thing has happened. Write them as physical events: materials delivered, framing complete, mechanicals roughed in and inspected, drywall hung, substantial completion.

Stay ahead of your own costs

Each draw should land before or alongside the spending it funds, not after. If drywall is drawn on completion of drywall, you have already paid the crew and the supplier out of your own pocket and you are financing the customer.

Front load the draws against your actual cash out. Materials for the whole job often arrive early and they are the biggest single outflow, which is what the deposit and first draw are for.

Deposits are regulated, so check before you write one

Several states cap the deposit a residential contractor may take. Some use a percentage, some a flat dollar amount, and some tie it to when work must start. Exceeding the cap can be a licensing violation, not just a contract problem.

Keep the final payment between 10 and 20 percent. Below 10 and the customer has no reason to sign off the punch list. Above 20 and you are funding the end of their job with your own money.

Questions people ask

What is a typical contractor payment schedule?

A 10 percent deposit, three or four progress draws tied to milestones, and 10 percent on completion is common for residential remodels. Big jobs use more draws, small ones fewer.

How much deposit can a contractor ask for?

It depends on your state. Several cap residential deposits by percentage or dollar amount. Ten percent is widely accepted and is inside almost every cap.

Should the final payment be big or small?

Between 10 and 20 percent of the contract. Small enough that you are not financing the job, big enough that the customer has a reason to complete the sign off.

Need the paperwork too?

Free Contractor Agreement Template, free, no signup, PDF Word and Excel.

Common sizes, worked out

The same calculator with the numbers already filled in, one page per size, each ending in its own material list.

Put this calculator on your own site

Free to embed. The only condition is the one line of credit already in the snippet, and there is no tracking of your visitors beyond a page view. Paste this where you want it to appear. It resizes itself.

It comes light, because most of the pages it goes on are light. If your site is dark, put ?theme=dark on the end of the iframe address, or ?theme=auto to follow whatever each reader has set on their own device.

Related calculators