What Is a Punch List? The Document That Decides When You Get Paid the Rest
The agreed list of small items still to be corrected before the work is accepted. It reads like a formality and it is not, because in practice the punch list is the gate on your final payment and on the release of your retainage.
Also called Snag list, Punch out list, Deficiency list.
Open the free punch list template Fill it in on the walk, from a phone if you like, and download the PDF or the Excel file. Free, no signup, no watermark.What it does
Near the end of a job the owner, or the architect, or both, walk the work and write down everything that is incomplete, damaged or not to standard. That list is the punch list, and correcting it is usually the last thing standing between you and the balance of the contract.
It serves a second purpose that matters more than the first. A signed punch list is a statement that everything not on it is accepted. That is the most valuable sentence in the document, and it is why you want the list written, dated and agreed rather than delivered as a running commentary.
Getting it in writing on the day of the walk is the whole discipline. Everything else on this page follows from that one habit.
Why an unwritten punch list never ends
A verbal punch list has no edge. Every subsequent visit by the owner adds an item, because a person walking a nearly finished building will always find one more thing, and nothing in the process says the list is closed.
The contractor then works for free, one small item at a time, while the final payment sits unreleased and the retainage sits behind it. The cost is rarely in any single item. It is in the trips, the reordering of other work, and the months the money is out.
A written list with a date stops this by converting an open ended obligation into a finite one. Items found later are still worth fixing when they are genuinely defects, but they are a warranty matter or a new instruction, not a reason to hold the balance of a contract.
Who walks it, who writes it, who signs it
On a small residential job it is the owner and you. On anything larger it is the architect or the owner's representative, usually with the general, and each subcontractor gets the slice of the list that belongs to their trade.
Whoever walks it, you want to be there and you want to hold the pen or at least a copy. A list written by the owner alone will contain items that were never in the scope, and separating those out afterwards is a much harder conversation than declining them on the walk.
Mark anything that is outside the scope as it comes up, on the list, in writing. Not refused, just noted as an extra to be priced. That keeps the walk moving and turns three arguments into one change order.
What the list actually unlocks
Final payment is the obvious one. Retainage release is the bigger one, because retainage is typically five to ten percent of the whole contract and it is often held until the punch list is signed off.
The list is also tied to substantial completion on most commercial contracts, and substantial completion is what starts the warranty period and stops any delay damages running. A job that drifts because the punch list is unresolved keeps those clocks in the wrong position.
So the punch list is not the tail end of the job. It is the switch that moves the money and the deadlines, which is why it deserves a form rather than a scrap of paper.
What every line needs
A punch list item with no location and no owner is a dispute waiting to happen. These six fields are what make a list closable.
- Item number
- So it can be referred to in an email without describing it again.
- Location
- Room, elevation or grid reference. Second bedroom, not upstairs.
- Description
- What is wrong and what done looks like. Touch up paint at architrave, not paint.
- Responsible trade
- Which sub owns it. On a general's list this is what turns one document into five.
- Date identified
- The date of the walk. This is the field that closes the list, because it dates the acceptance of everything not on it.
- Date corrected and accepted by
- Signed off line by line. A list where items are ticked but nobody signed is only half a record.
What it looks like
This is the blank form as this site actually prints it, drawn from the same file the download button gives you. It is not a picture of somebody else's document.
What to do with it
Questions people ask
What is the difference between a punch list and a snag list?
Nothing. Punch list is the American term and snag list is the British and Irish one. Deficiency list and punch out list turn up in the same role. If a document names remaining defects to correct before acceptance, it is a punch list whatever the heading says.
Who is responsible for creating the punch list?
The owner or the owner's representative, usually the architect on a designed job. In practice the contractor often drafts it first, walks it with the owner and agrees the final version, which is a better position to be in than receiving a list you had no part in writing.
Can an owner keep adding items to the punch list?
Not once it is agreed and dated, which is the reason to date it. Genuine defects found later are a warranty matter. New requests are a change order. Neither is a reason to hold the balance of the contract, and a written, signed list is what lets you say that with a document in your hand.
How long should a contractor have to complete a punch list?
Whatever the contract says, and if it says nothing, agree a period in writing when the list is issued. Two to four weeks is common on residential work. The point of agreeing it is not the deadline itself, it is that an open ended punch list keeps the retainage out of reach indefinitely.